Normal train traffic restored in Madurai

SR took up 27 days of work from February 9, 2023, including 20 days of pre-non interlocked working, and the entire work was culminated on March 7, a statement said.

DTNEXT Bureau

MADURAI: After the commissioning of newly doubled Thiruparankundram-Tirumangalam section under Madurai junction at a distance of 17.20 km and completion of modification of the station yards, the normal train traffic has been restored from Wednesday. SR took up 27 days of work from February 9, 2023, including 20 days of pre-non interlocked working, and the entire work was culminated on March 7, a statement said.

Visit news.dtnext.in to explore our interactive epaper!

Download the DT Next app for more exciting features!

Click here for iOS

Click here for Android

Iran says missiles targeted Netanyahu’s office, Israeli air force HQ

Indian Coast Guard escorts 3,741 pilgrims from Katchatheevu to Rameswaram

Industrial output growth slows to 3-month low of 4.8 pc in January

PCB considering financial penalties on Pakistan players for T20WC debacle