Normal train traffic restored in Madurai

SR took up 27 days of work from February 9, 2023, including 20 days of pre-non interlocked working, and the entire work was culminated on March 7, a statement said.

DT NEXT Bureau

MADURAI: After the commissioning of newly doubled Thiruparankundram-Tirumangalam section under Madurai junction at a distance of 17.20 km and completion of modification of the station yards, the normal train traffic has been restored from Wednesday. SR took up 27 days of work from February 9, 2023, including 20 days of pre-non interlocked working, and the entire work was culminated on March 7, a statement said.

Visit news.dtnext.in to explore our interactive epaper!

Download the DT Next app for more exciting features!

Click here for iOS

Click here for Android

Mekedatu dam construction will not be allowed: Minister CTR Nirmal Kumar

Police suspended over harassment plaint in Tirunelveli

Confirmed Ebola cases in Congo reach 282 as survivors describe their recoveries

Gold declines Rs 2,500 to Rs 1.6 lakh/10g amid fresh US-Iran tensions

Rescuers dig for bodies after massive mining explosives blast in Myanmar kills at least 38