Central Water Commission members visited Sathanur dam to review ongoing works under the DRIP (Dam Rehabilitation and Improvement Programme) presently underway, officials revealed on Saturday.

migrator

Tiruvannamalai

CWC director Pramod Narayanan accompanied by deputy director Chourab Charan accompanied by six engineers from Chennai along with assistant engineers from Tiruvannamalai and Sathanur dam went around the edifice.

The team members also inspected ongoing work on the dam’s 20 shutters which are being replaced at a cost of Rs 55 crore under a world bank funded project.

This is the first time that major works have been undertaken in the dam’s 62 years of service.

Officials expressed happiness and said a report would be submitted to the commission in New Delhi.

Visit news.dtnext.in to explore our interactive epaper!

Download the DT Next app for more exciting features!

Click here for iOS

Click here for Android

Madras University lecturers' evaluation boycott to delay UG results

Fire at Arumbakkam Metro Rail station triggers panic; no injuries, says CMRL

TN’s Hosur pitch meets competition as neighbouring states woo space firms

TN, IN-SPACe to set up Rs 100 cr space unit in Thoothukudi

Chennai: Bike hits barricade, Class 12 girl riding pillion with 16-year-old boy crushed to death by container lorry