Sathanur dam 
Tamil Nadu

CWC officials inspect Sathanur dam, review ongoing improvement works

Central Water Commission members visited Sathanur dam to review ongoing works under the DRIP (Dam Rehabilitation and Improvement Programme) presently underway, officials revealed on Saturday.

migrator

Tiruvannamalai

CWC director Pramod Narayanan accompanied by deputy director Chourab Charan accompanied by six engineers from Chennai along with assistant engineers from Tiruvannamalai and Sathanur dam went around the edifice.

The team members also inspected ongoing work on the dam’s 20 shutters which are being replaced at a cost of Rs 55 crore under a world bank funded project.

This is the first time that major works have been undertaken in the dam’s 62 years of service.

Officials expressed happiness and said a report would be submitted to the commission in New Delhi.

Visit news.dtnext.in to explore our interactive epaper!

Download the DT Next app for more exciting features!

Click here for iOS

Click here for Android

Heavy rain predicted in several dists; heat relief for Chennai

JACTO-GEO demands old pension scheme, repeal of interim payouts

Remarks on DMDK not criticism: VCK president Thol Thirumavalavan

Durai Vaiko's remarks against MK Stalin not right: KN Nehru

TNSTC to operate 2,655 special buses for weekend rush

SCROLL FOR NEXT