Chennai Metro Rail’s TBM Kurinji completes 1.08 km tunnel from Kolathur to Srinivasa Nagar

During the 1.08 km tunnel drive, the TBM had to negotiate a sharp curve with a radius of 230 metres and pass through varying geological conditions, ranging from soil and weathered rock to hard rock

DT NEXT Bureau

CHENNAI: The Chennai Metro Rail Limited’s tunnel boring machine (TBM) Kurinji broke through at Srinivasa Nagar Metro Station on Friday, completing a 1.08 km underground tunnel from Kolathur as part of the Phase II project. The tunnel is part of Corridor 5, which will connect Madhavaram in north Chennai with Sholinganallur in the south. 

During the 1.08 km tunnel drive, the TBM had to negotiate a sharp curve with a radius of 230 metres and pass through varying geological conditions, ranging from soil and weathered rock to hard rock. It also crossed more than 70 borewells and open wells in a densely populated residential area. 

CMRL said that the breakthrough was completed without disrupting public movement or traffic. The tunnelling work was executed by Tata Projects with funding support from the Japan International Cooperation Agency (JICA). The tunnel drive began on November 27 last year from Kolathur Metro Station.

The breakthrough marks a milestone in the construction of the underground section of Corridor 5 that spans 47 km, comprising 41.2 km of elevated tracks and 5.8 km of underground sections. The underground stretch includes five stations and two ramps. The corridor will connect several neighbourhoods across the city, linking north Chennai with the southern IT corridor.

Not by the book: 70,674 suspect titles, 30-day shortcut purchase

It makes no sense: Auto rides costlier than cabs in Chennai

Madras High Court slams delay in setting up open-air jail for women

Time to act against officials who fail to keep footpaths free

Guv-Shah 90-minute 'private' meet sparks talks of State's L&O discussion

SCROLL FOR NEXT