Chennai Metro Phase 2: CMRL completes pier work on Corridor 5 stretch

The stretch around Medavakkam includes some of the tallest piers in the package, reaching about 29 metres. The alignment crosses the existing Medavakkam Flyover at this height and includes a 57 metre steel girder span along a 125 metre radius curve.

DT NEXT Bureau

CHENNAI: Chennai Metro Rail Limited (CMRL) has completed the casting of all 513 piers for the 11.3 km Phase 2 Corridor 5 between Ullagaram and Elcot Metro stations.

The final pier, P814, was cast near Medavakkam-I Metro station.

The stretch around Medavakkam includes some of the tallest piers in the package, reaching about 29 metres. The alignment crosses the existing Medavakkam Flyover at this height and includes a 57 metre steel girder span along a 125 metre radius curve.

Medavakkam-1 and Medavakkam-2 Metro stations are also being built at about 29 metres above road level. CMRL is now progressing with the erection of the remaining U-girders and construction of station buildings.

95 killed, nearly 350 missing as massive flash flood sweeps through Nepal districts

Chennai: Auto unions hope for fare hike after 13-year wait

MPSC cancels Drug Inspector recruitment process over paper leak findings

India, US discuss ways to strengthen civil nuclear cooperation

Chennai gets 250 new low-floor buses worth over Rs 290 crore