Representative image 
Business

343 infra projects show cost overruns of Rs 4.5 lakh crore

“Also, out of a total of 1,438 projects in 2022, 835 projects were delayed,” the December 2022 report said.

DTNEXT Bureau

NEW DELHI: Procedural delay and other bottlenecks have led to Rs 4.5 lakh crore worth of cost overrun in as many as 343 infrastructure projects, each entailing an investment of Rs 150 crore or more, says the latest report from the Ministry of Statistics and Programme Implementation.

“Also, out of a total of 1,438 projects in 2022, 835 projects were delayed,” the December 2022 report said.

Reasons for time overruns as reported by various project implementing agencies include delay in land acquisition, delay in obtaining forest and environment clearances, and lack of infrastructure support and linkages.

Delay in tie-up for project financing, finalisation of detailed engineering, change in scope, tendering, ordering and equipment supply, and law and order problems were among the other reasons.

The report also cited state-wise lockdowns due to COVID-19 (imposed in 2020 and 2021) as a reason for the delay in the implementation of these projects.

Visit news.dtnext.in to explore our interactive epaper!

Download the DT Next app for more exciting features!

Click here for iOS

Click here for Android

Finalise SOP for political meetings, roadshows by Jan 5, Madras High Court directs government

India defeat South Africa by 30 runs, clinch T20I series 3-1

Tamilisai bats for Vijay's 'evil force' remark

SIR: Don't fall for panic mongering, EPS justifies 'purging' of voters

Chennai Corporation issues vending certificates, fixes vending fees