Kundankulam N-plant 
Tamil Nadu

Kundankulam N-plant 3, reactor pressure vessel installed

All the six units are built with Russian technology and equipment supplied by Rosatom.

IANS

Chennai: India's atomic power plant operator Nuclear Power Corporation of India Ltd (NPCIL) on Saturday placed the reactor pressure vessel for the 1,000 MW unit at Kudankulam in Tamil Nadu.

According to NPCIL, the reactor pressure vessel for Unit 3 was positioned at its designated place.

With this the project achieved a major milestone, NPCIL said.

The company Chairman & Managing Director Bhuwan Chandra Pathak, flagged off the event in the presence of M. Sankaranarayanan, Director (Finance), S. Jayakrishnan, Executive Director (Projects-LWR), Rajeev Manohar Godbole, Site Director, Kudankulam Nuclear Power Project (KKNPP) M.S. Suresh, Project Director, KKNPP-5&6, E. Chinnaveeran, Project Director, KKNPP-3&4, R.S. Sawant, Station Director, KKNPP-1&2 and other senior officials.

Currently, NPCIL has two 1,000 MW plants (units 1 and 2) functioning at Kudankulam, while four more (Units 3, 4, 5 and 6) are under construction.

All the six units are built with Russian technology and equipment supplied by Rosatom.

Visit news.dtnext.in to explore our interactive epaper!

Download the DT Next app for more exciting features!

Click here for iOS

Click here for Android

Finalise SOP for political meetings, roadshows by Jan 5, Madras High Court directs government

India defeat South Africa by 30 runs, clinch T20I series 3-1

Tamilisai bats for Vijay's 'evil force' remark

SIR: Don't fall for panic mongering, EPS justifies 'purging' of voters

Chennai Corporation issues vending certificates, fixes vending fees