Chennai Metro Rail Limited (CMRL) 
Chennai

CMRL Phase II: Final U-girder cast in Corridor-5

With 892 U-girders produced, the package has recorded the highest U-girder production among Phase II project packages.

DT NEXT Bureau

CHENNAI: The Chennai Metro Rail Limited (CMRL) has completed the casting of all precast elements, including the final U-girder, for Phase II Corridor-5 between Ullagaram and Sholinganallur.

A total of 3,126 precast elements have been cast, comprising 1,041 I-girders, 892 U-girders, 871 pier arm segments, 303 pier caps and 19 portal shells.

With 892 U-girders produced, the package has recorded the highest U-girder production among Phase II project packages.

The precast works involved 98,052 cubic metres of concrete, 18,550 tonnes of reinforcement steel and 3,010 tonnes of high-tensile strands, stated CMRL press note.

The scale was achieved through the collaboration of CMRL, general consultant AEON Consortium and contractor HCC-KEC Consortium.

“Work will now focus on installing the remaining U-girders and constructing entry and exit structures. These activities are progressing towards the timely completion of the Chennai Metro Phase II project,” added the press note.

Deepam to be lit at Tiruparankundram hill at 5 pm under retired judges' supervision

Left parties seek Constitution Bench hearing on Tiruparankundram Deepam case

Tiruparankundram row: Cockroach Janata Party leader accuses BJP of trying to communalise TN

INDIA bloc decides to oppose delimitation bill, says it is against SCs/STs, will end democracy

MDMK General Secretary Vaiko accuses BJP-led Centre of encouraging Karnataka’s Mekedatu Dam project

SCROLL FOR NEXT